Emergency work to replace two damaged rails on the Brighton Main Line means passengers on the route are being urged to only travel if necessary this Sunday morning.

Engineers will start work late on Saturday night between East Croydon and Redhill, replacing rails with hidden defects spotted by Network Rail’s ultrasonic test train. Leaving those defects unfixed could result in a broken rail.

For that reason, from around midnight to 2pm on Sunday there will be major changes to train services on the route. There will be an extremely limited train service with only one train every 90 minutes between London and Brighton, via Gatwick Airport. Challenges with bus driver availability due to COVID and major engineering work on other routes also means only a very limited replacement bus service will run between Redhill and East Croydon.

Tickets will be accepted on Metrobus route 100 between Redhill and Gatwick Airport and on TfL bus services between Redhill and East Croydon. For further travel advice, visit Southern or Thameslink’s websites.

It comes on top of major engineering work between Three Bridges and Arundel planned from Saturday 14 August to Sunday, 22 August, when £22m will be invested to improve stations and replace old signalling and track. Passengers travelling on the Arun Valley line over the 9-days are advised to plan ahead at networkrail.co.uk/ArunValley or at southernrailway.com

Network Rail and Govia Thameslink Railway’s joint network operations director, Mike Paterson, said: “We’re really sorry to be causing such disruption this Sunday, especially with engineering work elsewhere on our railway at Horsham.

“Our advice is to travel only if you absolutely have to while the work is taking place on Sunday morning, as we simply do not have the resources to run enough buses to carry everyone safely.

“We’ve got one line open, which will allow a very limited train service to run, but nowhere near what we would need to carry the normal number of passengers to the beach on a Sunday morning. Our team has tried to find different ways of getting this job done but we can’t put it off any longer and have to take this action now.

“Our test train picked up invisible defects inside two rails near Purley and the location of those rails means we will have to cut the damaged sections out and replace them.

“We’re keeping the line open until then by running trains more slowly, but that won’t work beyond a few days and we have to balance the need to carry passengers to the airport and the beach this weekend with our ability to do it safely.

“The nature of this problem means closing the line overnight Saturday and Sunday morning is the least-worst option.”

Journey planners will be updated on Saturday 14 August and passengers are advised to check their journeys before they travel for the latest information and the best journey option.

Notes to Editors

Both rails are part of a set of points at Stoat’s Nest Junction just outside Purley.

Normally, rail defects can be clamped and trains run slowly over the top until they can be replaced, but the location of both these faults means engineers have to replace them straight away.

Travel Advice

From 11:00 on Sunday 15 August , trains will start to run again with full service expected to resume by approximately 14:00.

Tickets will be accepted on Metrobus route 100 between Redhill and Gatwick Airport and on TfL bus services between Redhill and East Croydon.

Passengers holding tickets travelling between London and:

  • Stations on the East Coastway (Brighton and stations further east), can travel via St Leonards Warrior Square and use Southeastern services to/from London
  • Stations between Nutfield and Leigh to travel, can travel via Tonbridge and use Southeastern services to/from London

Topics

Categories


For more information, contact the press office on 0203 750 2031.

Govia Thameslink Railway

Govia Thameslink Railway (GTR) operates Thameslink, Great Northern, Southern and Gatwick Express services as follows:

  • Thameslink – cross-London services between Bedford/Peterborough/Cambridge and Brighton/Horsham/Littlehampton/East Grinstead, and between Luton/St Albans and Sutton/Wimbledon/Rainham; plus services between London and Sevenoaks
  • Great Northern – services between London and Welwyn, Hertford, Peterborough, Cambridge and King’s Lynn
  • Southern – services between London and the Sussex coast (Brighton, Worthing, Eastbourne, Bognor Regis, Hastings) and parts of Surrey, Kent and Hampshire (Ashford International, Southampton, Portsmouth)
  • Gatwick Express – fast, non-stop direct services between Gatwick Airport and London Victoria (currently suspended during the pandemic)

www.southernrailway.comwww.thameslinkrailway.comwww.gatwickexpress.comwww.greatnorthernrail.com

Govia Thameslink Railway

United Kingdom